Microsoft's new approach to data centers (I've worked in places with big data centers before with the halon gas and the full-length murals... and boy if that's not something to get the management types all excited...)
Starting with a Chicago-area facility due to open later this year, Microsoft will use an approach in which servers arrive at the data center in a sealed container, already networked together and ready to go. The container itself is then hooked up to power, networking, and air conditioning.
"The trucks back 'em in, rack 'em, and stack 'em," Chief Software Architect Ray Ozzie told CNET News. And the containers remain sealed, Ozzie said. Once a certain number of servers in the container have failed, it will be pulled out and sent back to the manufacturer and a new container loaded in.