April 24, 2001

 

 

Topic 13 PROJECT MANAGEMENT   I I  ( Administration)

 

  1. OBJECTIVES:

 

    1. Review homework

q Pre-contruction Agenda

q Quality Control Checklist

q Design Quiz#2

    1. Identify the most common causes of construction fatalities.
    2. Calculate the critical path in a network schedule.
    3. Select the appropriate scheduling technique for construction work.
    4. Be able to organize project information into a logical filing system.
    5. Create and maintain a change order log.
    6. Conduct a project close out.

 

  1. REFERENCES:
    1. Facilities Management: A Manual for Plant Administration Part IV Facilities Planning, Design, Construction and Administration, ed. By W.D. Middleton,1997.
    2. The Architect’s Handbook of Professional Practice Vol I-IV, ed by D. Haviland, 1994.
    3. APPA Commissioning Workshop, J. Heinz, 1997
    4. Construction Project management, R.H. Clough, 1998..
  2. TEXTS:
    1. A Guide to the Project Management Body of Knowledge ( PMI), By William Duncan 1996.

 

  1. WEB SITES:

 

    1. www.ces.clemson.edu/cica

 

 

  1. SUPPLEMENTS:
    1. Project Safety S 13-1
    2. Project Documents S 13-2
    3. CPM Schedules S 13-3 
    4. Change Order log S 13-4 & 13-4a
    5. Project Close Out S 13-5

 

  1. PREASSIGNMENTS: None

 

  1. HOMEWORK: DUE Monday April 30 by 10 AM.  Bring your own copy to class as well.

 

    1. Put Supplement S 13-1 in Project Book format.
    2. Put Supplement S 13-2 in Project Book format.
    3. Put Supplement S 13-3 in Project Book format.
    4. Put Supplement S 13-4 in Project Book format.
    5. Put Supplement S 13-5 in Project Book format.
    6. Turn in your Project Book in class, after your presentation is made.