TOPIC : _10_- Design III ( AE Negotiation) 

  1. OBJECTIVES:
    1. Review homework

q Designer rating

q Designer billable rates

q Designer fee estimate

q CSI spec for paint

    1. Analyze designer fee proposal and create negotiation strategy.
    2. Document results of fee negotiations.
    3. Create detailed time schedule from planning through final work completion.
    4. Perform constructability review of project plans.
    5. Create submittal log for construction phase.
  1. REFERENCES:
    1. Facilities Management: A Manual for Plant Administration Part IV Facilities Planning, Design, Construction and Administration, ed. By W.D. Middleton,1997.
    2. The Architect’s Handbook of Professional Practice Vol I-IV, ed by D. Haviland, 1994.
  1. TEXTS:
    1. How to Estimate with Means Data & Costworks, S.A. Murbarak, 1999.
  1. WEB SITES:
    1. www.admin.ufl.edu/division/cp
  1. SUPPLEMENTS:
    1. Designer Fee Proposal  S 10-1
    2. Detailed Project Schedule S 10-2
    3. Spread Sheet for Project Schedules S 10-2a
    4. Constructability Review of Plans S 10-3
    5. Submittal Log S 10-4
  1. PREASSIGNMENTS: None
  1. HOMEWORK: DUE Monday April 9 by 10 AM.  Bring your own copy to class as well.
    1.  Using Supplement S 10-1 and your class notes, write a negotiation documentation letter.  Put it in Project Book format.
    2. Using Supplements S 10-2 and 10-2a create a detailed planning schedule.  Put it in Project Book format.
    3. Using Supplement S 10-3 complete the constructability review of the Health Center.  Put in Project Book format.
    4. Using Supplement S 10-4 create a submittal log for the Health Center and put it in Project Book format.